Recovery Reset Plan

Stabilise a troubled project and create a credible reset baseline.

When to use

Use after exception, sustained amber/red status, supplier failure, or loss of confidence.

Sample suggested content

Project example: Troubled delivery reset

  • Current condition: Red; plan no longer credible and ownership unclear.
  • Stabilise: Freeze non-essential change, confirm decision owners, rebaseline critical work.
  • Decision ask: Sponsor approves reset plan and weekly recovery checkpoint.

Minimum version

  • Current condition
  • Stop/continue recommendation
  • Stabilisation actions
  • Reset controls
  • Decision asks

Fuller version

  • Root causes
  • Contract implications
  • Reforecast
  • Recovery governance
  • Confidence checkpoints

Field guide

  • Diagnosis
  • Viability
  • Immediate actions
  • Reset baseline
  • Governance
  • Decision

Tailoring notes

  • Use Recovery control level by default
  • Shorten reporting cadence until confidence improves

Common mistakes

  • Resetting dates without changing controls
  • Treating recovery as a communications exercise